Plans are underway in Minsk to build a new highway connecting the Kastrychnitski and Maskouski districts. The project provides for the extension of the so-called third ring road: the roadway will begin at Churlionis Street and extend to Karzhaneuski Street. This was reported by Siarhei Panou, head of the state enterprise "Hardarbud."

The new route will begin at Churlionis Street, cross Karalinskaya Street at grade, and then follow the natural terrain toward the railway. An overpass will be constructed above it to connect with Karzhaneuski Street. An exit ramp to Landar Street is also planned. Landar Street itself will be reconstructed and shifted slightly closer to the railway to ensure the proper operation of the left-turn ramp from the overpass.
The highway will have six lanes—three in each direction. The project includes building an overpass over the railway and relaying heating, water supply, and electrical utilities. At the same time, existing facilities will continue operating without interruptions.
Parking areas and public transport stops, as well as pedestrian walkways and bicycle lanes, will be constructed alongside the road.
The enterprise expects to begin preparatory work at the site in late 2026. Main construction, involving large-scale earthworks, is scheduled to start at the end of January 2027. They hope to open traffic on the new highway in 2028.
Construction of the overpass will be similar to the work carried out on the Kolesnikov – Ratamskaya overpass. The sequence includes earthworks, the erection of piers, crossbeams, and girders, as well as surfacing the roadway. In addition, a section of Karzhaneuski Street will be upgraded.
The construction may impact public transport operations: stops may be relocated, and temporary detour routes may be established around active work zones. However, overall route directions will remain unchanged.
Plans call for building the overpass around the clock. Because the work will take place near residential neighborhoods, the noisiest activities will be carried out during daylight hours whenever possible, while avoiding loud operations at night.
The project also provides measures to minimize inconvenience to local residents. Authorities promise to maintain traffic flow throughout all phases of construction and to give advance notice of any possible pedestrian restrictions or changes to the transit system. For residential buildings within the acoustic impact zone, officials are considering replacing existing windows with soundproof ones.
Access to public facilities—kindergartens, schools, and clinics—must be maintained throughout the entire construction period.