They designed cowsheds and a battery plant, and now they've taken on Baroque. They intend to strip all the plaster from the majestic Jesuit Collegium in Pinsk — and it was painted with frescoes
27 million rubles have been allocated for the renovation of the Museum of Belarusian Polesie, and the works will last almost four years. Nasha Niva examined the history of the monument — we explain how this massive edifice collapsed twice during construction and what threatens it under the current project.

The local newspaper *Pinski Vesnik* reported on November 16 about the start of construction works in the historical building of the Museum of Belarusian Polesie at 22 Lenin Square in Pinsk. Earlier, as we reported, the Department of Culture of the Brest Regional Executive Committee announced plans to carry out major repairs on this Baroque architectural monument.
According to design documentation, the works are scheduled for almost four years — until July 2030.

What the 27 Million Rubles Will Be Spent On
The project is funded entirely from the state budget. According to the cost estimate, almost 27 million rubles (about $9 million) will be spent on its implementation.

Of the approved 27 million, exactly 10 million rubles is earmarked directly for the creation of a new museum exposition. The remaining 17 million rubles will go toward construction and installation works, equipment procurement, and design. The largest expense items are general construction and dismantling works inside the building and roof replacement for 5.44 million rubles, and facade repair for 1.79 million.

The installation of fire and security alarms will cost 562 thousand, a complete replacement of electrics and lighting 535 thousand, upgrading heating and ventilation systems 431 thousand, and landscaping of the adjacent 0.8-hectare territory 253 thousand rubles. The rest will go to the academic supervisor, the development of specialized restoration solutions, and architectural supervision.
From Calf Barns and a Battery Plant to Baroque Vaults
As follows from the conclusion of the state construction expertise, the general designer of the capital renovation is the Pinsk private enterprise Ahramashdetal.
According to information on the company's official website, it has been operating since 2007 and specializes primarily in industrial and agricultural construction.

The main source of pride in the company's portfolio is the design of the iPower battery plant near Brest, the Belinvesttorg-Splav lead plant in Beloozyorsk, and a plastic battery components plant in Pinsk, as well as dairy farms, cowsheds with milking blocks, and calf barns for 300–1,050 head for farms across the Brest and Minsk regions. Among public buildings in the designers' portfolio are the PinaPark shopping center, the reconstruction of a hospital in Davyd-Haradok, major repairs of two Pinsk schools, and a modern Orthodox church on Kraynyaya Street in Pinsk.
Since, according to the Code on Culture, design work on historical and cultural heritage sites can only be performed by organizations that employ certified specialists, the specialized enterprise RestawratsyyaInvest from Brest was subcontracted to develop one set of drawings. A specialist from this company, Kazakow, served as the academic supervisor and chief architect of the restoration project. However, these drawings cover only the exterior facades, window replacements, and entrance doors.

All other sections of the project, including drawings for interior work in spaces with ancient vaults, basements, and the attic, were developed by Ahramashdetal itself. And an obvious contradiction arose in the documents between the approaches of the two developers.
In the bill of restoration and renovation works on facades compiled by Brest's RestawratsyyaInvest, a delicate methodology for preserving the authentic surface of the walls is prescribed.
The restorers require tapping all 4,144 square meters of preserved lime plaster, and upon discovering cracks or flaking, gently removing only the upper degraded layer of 1 to 5 millimeters using metal scrapers or a milling cutter.
Then the surface was to be moistened with water, cracks routed out, filled with lime mortar mixed with marble or stone dust, and smoothed down. The restorers permitted stripping plaster down to the brick only on weakened, hollow-sounding areas and spots with old cement patches — and ordered this to be done over small areas with light hammer taps until firmly adhered parts of the old plaster appear. Such areas with complete loss of plaster down to the brickwork on the facades amounted to only 87.52 square meters.
However, in the conclusion of the state construction expertise, which is based on the Ahramashdetal project, a radically different decision is recorded.
The section on exterior and interior finishing literally states: "100% dismantling of existing plaster compositions on the building's facades, including the plinth, down to the substrate, followed by the application of new plaster made from a mixture based on a cement-free lime binder."
Immediately below, an identical requirement is stated for the interiors: "100% dismantling of existing plaster compositions on the interior surface of walls and ceilings down to the substrate, followed by the application of new plaster."

Why such a discrepancy arose in the documents is unclear. Perhaps the experts simply lumped together the delicate cleaning of facades and the complete stripping of plaster inside the building. But as a result, the official expert conclusion mandates precisely the 100% removal of all plaster down to the brick — both outside and in the interiors.
What the workers of the Pinsk Repair and Construction Administration will be guided by on the scaffolding — the cautious methodology of Brest restorers using scrapers, or the direct note from the expertise specifying "100% dismantling down to the substrate" — remains an open question.
As for the interior halls and 17th-century groin vaults, no alternatives were left at all: they are being repaired according to Ahramashdetal drawings, where all the old plaster is unconditionally slated for demolition down to bare brick.
The entire project was officially approved by the Ministry of Culture of Belarus, which issued a positive conclusion on June 5, 2026.
Jesuit Roman Archives Say There Were Frescoes on the Facades
Meanwhile, the complete stripping of plaster without prior exploratory restoration probes for paintings could lead to the irreversible loss of valuable 18th-century murals.
In 2003, in the Krakow academic collection *Sztuka Kresów Wschodnich*, Polish architectural historian and Jesuit Jerzy Paszenda published a thorough study of the Pinsk collegium based on primary sources — the collegium chronicles sent every three years from Pinsk to the Central Archives of the Society of Jesus in Rome.
In these Roman chronicles, Paszenda discovered two direct pieces of evidence that the exterior facades of the Pinsk collegium during the Grand Duchy of Lithuania era were decorated with fresco paintings on plaster.
The first record dates to 1726: the chronicler noted that in that year the frontal part of the collegium on the church side — that is, the northern end facade with the Baroque pediment — was completed and was "decorated with painting on plaster" ("ozdobiono malowidłem na tynku").
The second record dates to 1755: back then the entire collegium building was whitewashed on all sides, and its main western facade, facing toward the former castle and today's Lenin Square, was repaired and additionally adorned with figurative or decorative murals ("ozdobiono malowidłami").

There is no mention in the documentation and cost estimates that any searches for these overpainted frescoes of 1726 and 1755 were carried out on the facades or inside the building prior to the current repairs.
A total of 135.3 thousand rubles was spent on all preliminary investigations prior to design in 2025: this sum included historical and archival research, architectural and archaeological surveys, laboratory testing of construction materials, and structural inspections.
During the study of the walls, partially walled-up historic openings were discovered — the project provides for opening them up with "blind windows" installed in place of the bricked-in niches, as well as recreating lost profiled cornices, belts, and pediments using templates.
As Jerzy Paszenda noted, the ground floor corridors on the courtyard side originally featured open arcade galleries, which were only later enclosed by thin walls.


Since reaching the upper tiers before repairs began was technically impossible without scaffolding, the restorers included a requirement in the drawings: after dismantling later layers where decoration is to be restored, builders are obliged to summon a representative of the designer's supervision for documentation.

Two Construction Disasters of the 17th Century
The Roman archives of the Jesuits also make it possible to clarify and correct a number of myths circulating in Belarusian guidebooks and even included in the official historic and cultural passport drawn up in 2012 by "Brestrestawratsyyaprayekt".
For instance, in the BTI technical passport and state expertise materials, 1631 is listed as the construction year of the collegium, and the monument's passport asserts that construction in 1651–1675 was directed by "architect of the painterly craft" Mateusz Falkowski.
However, according to the order's archival documents, the Jesuits, led by the first superior Marcin Krasnodębski, arrived in Pinsk at the invitation of sub-starosta Mikołaj Jelski only on October 10, 1632, and lived in wooden structures for a long time.

After Jelski's death, the foundation was taken over by Pinsk starosta and Grand Chancellor of Lithuania Albrycht Stanisław Radziwiłł and his wife Regina Eisenreich, who built a brick church between 1636 and 1647. Moreover, because there was neither stone nor suitable clay without marl impurities around Pinsk, Princess Anna Korecka-Radziwiłł specifically granted the Jesuits permission in 1634 to bake bricks for construction in her Kletsk estates.
Chancellor Radziwiłł allocated 40,000 zlotys for the construction of the masonry collegium only in 1651 — the solemn consecration of the cornerstone took place on September 27, 1651, and foundations were laid by the end of December.
However, due to war, Cossack raids — in 1657 Cossacks tortured to death Pinsk preacher Andrew Bobola, and on July 4, 1660 burned down the entire monastery and school — and another fire in 1663, the actual erection of masonry walls began only in 1667, when the monks concluded that constantly rebuilding burned wooden houses was far too expensive.

The southern wing along the Pina River was built first over nine years (1667–1675), constructed immediately to the full height of three stories.
In 1671, the first construction disaster struck here: the newly vaulted third-story ceilings collapsed all the way to the ground, halting the work; and in 1673 the monks were forced to hastily surround the site with a defensive wall for protection against Cossacks.
The southern wing was completed only in 1675.
The second, western wing began construction in 1689. In 1692, construction was halted due to the absence of an architect,
and in 1696, when the walls had already reached the third floor, a second catastrophe occurred. As the chronicler recorded, due to an error by an inexperienced architect, a too-wide and flat 19-meter arch over the ground-floor refectory could not bear the weight of the new upper-floor wall erected upon it and collapsed, causing several hundred florins' worth of damage.
This accident froze the completion of the western wing for almost three decades: half of the walls were vaulted only in 1714–1716, and work at the collapse site resumed only in 1725–1738, when Brother-Apothecary Mateusz Bösner was the construction prefect.

It was this catastrophe that explained the origin of the collegium's famously deep foundations: in 1730, an invited architect declared to the Jesuits that "one cannot even think of a refectory here" and ordered the hall divided in half by erecting a new load-bearing wall down the middle, 32 cubits long and 45 cubits high — approximately 19 by 27 meters respectively.
Since no basements existed in the northern part of the wing along a length of 30 meters, the foundations for this new internal wall were sunk into the ground 6 meters below the ground-floor level. Next to this wall, a 12-meter theology hall was placed on the second floor, and a 19-meter library on the third.

Jerzy Paszenda also provides an interesting explanation for the hexagonal tower at the southwestern corner of the building. Unlike the palace towers of the Vasa era, the Pinsk tower is lower than the main edifice and has windows and a small functional chamber only at the second-floor level. Its entire lower section, up to a height of 12 meters from the ground — the level of the high cellars and the ground floor — is a solid blank wall acting as a massive corner buttress on the river slope.

The researcher notes that the collegium building clearly remained unfinished: the eastern end of the southern wing has neither a similar tower nor even a masonry Baroque gable-pediment; thus, it is possible the Jesuits originally envisioned an enclosed quadrangular complex around an inner courtyard, with the school and pharmacy with laboratory located in separate adjacent buildings.
After the suppression of the Jesuit Order in 1773, the Commission of National Education divided the complex in 1786 among three users: the western wing was given to a secular school, the eastern part and the church unfinished after a fire to the Uniate Bishop Jachim Harbacki for a cathedral, and part of the courtyard to Pinsk starosta Chomiński for a chancellery.
After the Third Partition of the Polish-Lithuanian Commonwealth in 1800, the complex was transferred to the Orthodox Epiphany Monastery and theological school.
In 1919, the Jesuits returned to the buildings, but on September 21, 1939, when the Red Army entered Pinsk, Soviet artillery shelled the church from three sides for an hour and forty minutes — one tower was knocked down completely, the second half-destroyed, and the roof burned; subsequently, in the 1950s, the shrine was completely demolished.
As for the collegium building itself, after World War II it was occupied by a naval communications school and NKVD structures; from 1965 an art gallery operated there, and after the restoration of 1981–1996, the building was transferred to the Museum of Belarusian Polesie.
What Specifically Will Be Done by 2030


As can be seen from recent photos, builders began work on the attic and roof: fresh timber is already being delivered, scaffolding has been erected, and old ventilation pipes have been dismantled. Because the interior corridor walls of the second and third floors rise six meters above the vaults and serve as supports for the roof, the Jesuits were able to significantly reduce the amount of timber in the roof trusses at the time.


Now all rotted wooden rafters and roof battens will be completely replaced, precarious beams reinforced, and the wooden floor in one attic section replaced with a monolithic slab over steel beams. The tall mansard-like two-tier hip roof, which in the 18th century was covered with shingles and tiles, and from 1837 with sheet metal, will once again be covered with clay S-profile pantiles. The curvilinear parapets of the Baroque gables and dormer windows will be clad in sheet copper.
Downspouts, cornices, and flashings will be made of galvanized steel with a matte brownish-red coating. As restorers explain in notes to the drawings, in the 17th–18th centuries, tin flashings on the collegium were painted with a common natural mineral pigment — red lead (iron minium) — which simultaneously protected the metal from rust and gave it a characteristic reddish-brown hue.

Cracks in the facade masonry and on the underside of the vaults will be routed out and reinforced with metal anchors concealed in chases. After painting, the color palette of the facades will remain close to the present one: warm beige Palazzo 240 for the main walls, white pilasters and cornices, gray plinth — yet another clear sign that the facades were not investigated prior to the work.

Most of the old window units will be replaced with custom-made single-chamber double-glazed units of glued oak. On the exterior, the oak frames will be finished to look like "aged oak", and painted white on the interior.
At the same time, eight historical window units preserved in fair condition will not be replaced — they will merely be stripped of old paint and restored on site.
For all windows, designers selected antique-style hardware in matte or antique bronze with decorative handles.
In the interiors, historical staircases with decorative metal railings will be restored, marble, granite, and plank floors polished, and new parquet and ceramic tiles laid in some halls. The building will receive completely new utility networks, modern ventilation with air heating and humidification for museum halls and storage depositories.
After completion of the works in 2030, the Museum of Belarusian Polesie will occupy the entire collegium building, including the third floor, which it previously shared with a children's choreography school.