Lights are already being turned on on the overpass between Kamennaya Horka and Lebiadziny in Minsk PHOTO FACT
In Minsk, the construction of an overpass in the area of Kalesnikava and Ratamskaya streets is nearing completion. Lighting is already being turned on in the evenings on the bridge, indicating the final stage of landscaping the area. Real estate expert Natallia Litouskaya shared recent photos of the construction sent in by her subscribers.

As recently as November 9, the completion of the project was estimated at 95%. At that point, they were just starting to install lighting poles. Now, work continues around the clock. Vehicular traffic on the new bridge is expected to open before the end of 2026.

The overpass will connect the Lebiadziny neighborhood with Kamennaya Horka. Its total length will be more than 380 meters, and its width will range from 41.3 to 47.8 meters. The project provides for three lanes of traffic in each direction, as well as additional exit lanes.
This bridge has become the first new railway overpass in many years to be built from scratch in Minsk. Most similar structures in the capital were erected back in Soviet times. In addition, the new bridge will become only the second vehicular railway crossing in Minsk outside the central part of the city—between the Second Ring Road and the MKAD. The first such facility is located in Stsyapyanka, where the roadway passes underneath the railway tracks.
They designed cowsheds and a battery plant, and now they've tackled the Baroque. They plan to knock off all the plaster from the magnificent Jesuit Collegium in Pinsk — yet it was adorned with frescoes
Comments